New Bondi Road Duplex | Progress Video 3
This week's progress includes electrical lighting, kitchen joinery and bench top, paint work completed on all walls, front fence installation, gas cylinder & meter, cabinets...
This week's progress includes electrical lighting, kitchen joinery and bench top, paint work completed on all walls, front fence installation, gas cylinder & meter, cabinets...
This week we look at the progress of our New Bondi Road Duplex's interior finishes, the lift commission, side panelling, concrete steps and steel/glass stair...
Welcome to our newest renovation/building progress series: New Bondi Road Duplex! This project has been ongoing for 15 months, and is expected to continue for...
Domus Homes is starting a progress vlog at Dover Heights in Sydney, Australia! Throughout this series you'll watch the process from the very beginning, starting...
Domus Homes is starting a progress vlog at Dover Heights in Sydney, Australia! Throughout this series you'll watch the process from the very beginning, starting with...
Today''s video looks at a freshly set concrete slab and staircase at the front, the cantilevered timber deck at the back, concrete slab waterproofing at...
This is the second progress video of our Bondi Junction Apartment Renovation progress series. Today we look at the interior demolition progress, as the builders...
Domus Homes is starting a progress vlog at our Randwick Semi in Sydney, Australia! You'll get to see the tail-end of this project during its...
Domus Homes is starting a progress vlog, at our Bondi Junction Apartment in Sydney, Australia! We'll be showing you the in's and out's of renovating...