Progress to date (23 March, 2021):
First Floor Level:
- Eaves installed
- Fascia boards installed and painted
- Gutters installed
- Roof tiles installed
- External render completed
- Internal plumbing & electrical rough in completed
- Wall insulation completed
- Internal gyprock started
Ground Floor Level:
- Structural steel installed
- Roof frame installed
- Window openings ongoing
Next activities are:
- Drop the scaffold
- Install sarking and roof tiles
- Install the external doors & windows